Issue

An unexpected error occurs when attempt to create a serial Flow schedule even though "Linked Tasks" is disabled in Site or Server Level Settings. See Site level or Server level Settings for more information.
 

Environment

  • Tableau Server 2022.1-2023.1

Resolution

Option 1

Upgrade to Tableau Server 2022.3.6, 2023.1.2 or newer versions.

Option 2

Enable "Linked Tasks" in Site or Server level Settings. Before switching the Execution to Serial, make sure to uncheck the Linked Tasks option.

User-added image

Cause

This is a known issue that is resolved in more recent version of Tableau Server.
 