Sites set to the Mexico city timezone are having scheduled jobs running 1 hour ahead of schedule
Published: 16 May 2023 Last Modified Date: 29 May 2023
Issue
Automated jobs will run one hour ahead of schedule during daylight time if the site is set to the Mexico City timezone.
Environment
Tableau Cloud
Resolution
As a workaround, select an equivalent timezone in UTC - 6:00 such as Guatemala. Guatemala does not observe daylight savings time and instead observes Central Standard Time all year round.
Cause
As of October 2022, Mexico City no longer observes daylight savings time. This change has not been reflected in the Tableau products yet. This is a known issue that is being addressed by the development team.